Largest data center market in the world. By-right data center development was eliminated in March 2025; data centers now require a special exception (or rezoning) with public hearings. Loudoun is a VSMP authority (administers stormwater and E&S locally). Durations are estimates from public process descriptions, not observed county data; the playbook should be refined from closed projects.

Sources (5)

DocumentVersionEffectiveNotes
Loudoun County Facilities Standards Manual (FSM)——Engineering design standards for site plans, stormwater, E&S, roads and utilities. Check the current revision at filing.
Loudoun County Land Subdivision and Development Ordinance (LSDO)——Site plan (STPL) submission, review and approval procedure.
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination)2023 ZO, 2025 data center amendment2025-03-12Effective date is approximate (Board action March 2025 per Holland & Knight summary); verify against the adopted ZOAM. Special exception required for data centers in all districts where previously by-right.
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office2021 VUSBC / 2021 SFPC2024-01-18Effective date of the 2021 VUSBC is as commonly reported (Jan 18, 2024); verify. The VUSBC incorporates the 2021 I-codes with Virginia amendments; NFPA 855 (ESS), NFPA 30 (flammable liquids) and IFC Ch. 12 apply via the fire code.
Virginia public hearing advertisement and notice requirements for zoning actions (Va. Code § 15.2-2204) and Loudoun hearing calendar——Non-compliant hearing advertisements voided the Prince William Digital Gateway rezoning (Aug 2025; affirmed Mar 31, 2026). Treat notice compliance as a veto point with its own evidence file.

Requirement classes (17)

Triggers are evaluated against project inputs; durations are typical working days.
CodeTitleGateCategoryAsset classesTriggerDaysVetoPredecessorsSource / clause
LC-NOISE
Noise study (generator and mechanical plant)
Acoustic study of standby generator testing and cooling plant against the county noise standards. Noise is a recurring opposition theme and a redesign-and-re-review driver; the study is typically a condition of the special exception and is re-run if the generator or cooling spec changes.
Evidence: Acoustic report with modeled property-line levels; mitigation design if limits are exceeded.
EntitlementZoningData centerApplies when standby generators are proposed (generator count >= 1)40LC-PREAPP, TEN-GEN
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination)
Loudoun Zoning Ordinance, performance standards (noise)
LC-NOTICE-PLAN
Notice and hearing compliance plan
Written plan for every statutory notice (newspaper advertisement, adjacent-owner mail, posting) with dates, text and proof of publication, assembled as an appeal-ready evidence file. A single defective ad voided the ~2,100-acre Prince William Digital Gateway rezoning in Aug 2025 after approval in Dec 2023; the county spent $1.7M defending it. Universal class: applies to every asset class that needs a public hearing.
Evidence: Notice schedule; affidavits of publication; mailing list with certified-mail receipts; photos of posted signs; counsel sign-off that each notice matched the statute in force on the hearing date.
EntitlementZoningallAlways applies15VetoLC-PREAPP
Virginia public hearing advertisement and notice requirements for zoning actions (Va. Code § 15.2-2204) and Loudoun hearing calendar
Va. Code § 15.2-2204 (advertisement of plans, ordinances; notice to adjacent owners)
LC-PREAPP
Pre-application meeting with Planning & Zoning
Required pre-application conference with county staff before a special exception, rezoning or site plan filing. Establishes the application type, required studies (traffic, noise, fiscal) and the hearing track. Loudoun's process is the start of the statutory clock; nothing else files before it.
Evidence: Pre-application meeting notes from county staff listing required submittals and studies.
EntitlementZoningallAlways applies20—
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination)
Loudoun Zoning Ordinance, application procedures (pre-application conference)
LC-PUSHBACK
Owner pushback / waiver decision log
Universal class. A standing log where the owner records each requirement it intends to push back on, seek a waiver for, or consolidate across agencies, with the decision, who made it and the days saved estimate. Keeps procedural accretion visible and negotiable rather than silently absorbed.
Evidence: Decision log entries with date, requirement, decision, rationale and estimated schedule impact.
EntitlementOtherallAlways applies5LC-PREAPP
—
LC-SPEX
Special exception / rezoning approval (data center use)
Discretionary legislative approval with Planning Commission and Board of Supervisors public hearings. Loudoun eliminated by-right data centers in March 2025, so every new campus is a hearing item with conditions (proffers, noise, screening, phasing). Duration estimate covers staff review cycles and two hearing bodies; actual time depends on the hearing calendar and opposition.
Evidence: Board of Supervisors approval resolution with adopted conditions/proffers; signed condition sheet; hearing minutes.
EntitlementZoningData centerAlways applies200VetoLC-PREAPP, LC-NOTICE-PLAN, LC-TIS, LC-NOISE, DOM-CAPACITY
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination)
Loudoun Zoning Ordinance, special exception uses and procedures (2025 data center amendment)
LC-TIS
Traffic impact study
Traffic impact analysis scoped with the county and VDOT for the entitlement application. Data centers carry low operating traffic but heavy construction traffic; the study scope is set at the pre-application meeting.
Evidence: Scoping agreement; TIS report accepted by county transportation staff and VDOT.
EntitlementZoningallAlways applies60LC-PREAPP
Loudoun County Facilities Standards Manual (FSM)
Loudoun FSM / VDOT Traffic Impact Analysis Regulations (Chapter 527)
LC-APPEAL
Appeal period expiry on entitlement approval
Statutory window for a challenge to the legislative approval to be filed. Lenders and most counterparties will not close until the approval is final and non-appealable. Virginia's window is commonly 30 calendar days from the decision; confirm with counsel for the specific action. Universal class.
Evidence: Counsel letter confirming the appeal period has run with no filing (docket search attached).
PermitZoningallAlways applies22LC-SPEX
Virginia public hearing advertisement and notice requirements for zoning actions (Va. Code § 15.2-2204) and Loudoun hearing calendar
—
LC-ESC
Erosion and sediment control plan approval
E&S plan under the Virginia Erosion and Sediment Control Regulations, administered by the county. State threshold is 10,000 sq ft of disturbance; the county may apply a stricter one. Often sequenced late; put it on the schedule with the site plan.
Evidence: Approved E&S plan; responsible land disturber certification on file.
PermitStormwaterallAlways applies30LC-SITEPLAN
Loudoun County Facilities Standards Manual (FSM)
Virginia Erosion and Sediment Control Regulations (9VAC25-840); Loudoun FSM
LC-SITEPLAN
Site plan (STPL) approval
Engineering site plan reviewed against the FSM and LSDO and the entitlement conditions: grading, utilities, stormwater concept, access, landscaping and lighting. Multiple review cycles are normal; each cycle is a re-submission. The Section 404 determination should be in hand so the limits of disturbance are final.
Evidence: Approved and signed site plan set; condition compliance matrix; bond/agreement executed.
PermitZoningallAlways applies120LC-SPEX, LC-APPEAL, FED-404-NWP, FED-404-IP
Loudoun County Land Subdivision and Development Ordinance (LSDO)
Loudoun LSDO, site plan review procedure; FSM design standards
LC-SWM
Stormwater management plan approval (VSMP authority)
Post-construction stormwater (water quantity and quality) plan reviewed by Loudoun as the local VSMP authority under the Virginia Stormwater Management Program regulations. Required for land disturbance of one acre or more (state threshold).
Evidence: Approved SWM plan and computations; maintenance agreement recorded.
PermitStormwaterallApplies when land disturbance is one acre or more (site acreage >= 1)45LC-SITEPLAN
Loudoun County Facilities Standards Manual (FSM)
Loudoun FSM stormwater chapter; Virginia Stormwater Management Program Regulation (9VAC25-870)
LC-FIRE-REVIEW
Fire marshal plan review: lithium-ion UPS (NFPA 855), bulk diesel (NFPA 30), responder access
Fire Marshal's Office review of energy storage / Li-ion UPS under NFPA 855 and IFC Ch. 12, bulk diesel storage under NFPA 30, clean-agent suppression and fire apparatus access. Interpretations vary by jurisdiction; secure them in writing early because re-review after a design change is common.
Evidence: Fire marshal review letter; hazard mitigation analysis for ESS (NFPA 855); tank permit for diesel storage.
ConstructionFireData centerApplies when generators with on-site diesel storage are proposed (generator count >= 1); battery MWh is reviewed in the same package40LC-SITEPLAN, TEN-GEN
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office
2021 SFPC / VUSBC; NFPA 855; NFPA 30; IFC Ch. 12
LC-PERMIT-FOUND
Foundation (early-start) building permit
Phased building permit for foundations under the 2021 VUSBC, issued ahead of the full shell permit at the building official's discretion. Each phased permit is its own review cycle.
Evidence: Issued foundation permit; approved structural drawings.
ConstructionBuildingallAlways applies30LC-PERMIT-GRADING
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office
2021 VUSBC, phased/partial permits
LC-PERMIT-GRADING
Grading / land disturbance permit
First of the phased permits. Requires approved SWM and E&S plans, VPDES construction general permit coverage and performance bonds. Lets mass grading start before building permits.
Evidence: Issued grading permit; bond receipt; pre-construction meeting minutes.
ConstructionBuildingallAlways applies20LC-SWM, LC-ESC, DEQ-VPDES-CGP
Loudoun County Land Subdivision and Development Ordinance (LSDO)
Loudoun LSDO / FSM, land disturbance permit
LC-PERMIT-SHELL
Building shell permit
Full building permit for the shell. For generator fleets, VA DEQ Clarification 2025-03 limits what may be built before the air permit issues, so the air permit is a predecessor here. Fire marshal review of the generator yard, diesel storage and ESS must be complete.
Evidence: Issued building permit; approved plan set; fire marshal approval letter.
ConstructionBuildingallAlways applies45LC-PERMIT-FOUND, LC-FIRE-REVIEW, DEQ-AIR-SM, DEQ-AIR-MAJOR, DEQ-AIR-PSD
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office
2021 VUSBC, permit application and plan review
LC-CO
Certificate of occupancy by phase / data hall
Phased CO (or temporary CO) per building or data hall after all final inspections including fire. Tenant delivery milestones usually key off this document.
Evidence: Issued CO/TCO per phase; final inspection sign-off sheet.
Energization / occupancyBuildingallAlways applies15LC-INSPECT-ELEC, DOM-ENERGIZE
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office
2021 VUSBC, certificates of occupancy
LC-INSPECT-ELEC
Electrical final inspection and utility release
County electrical inspection of the service entrance and switchgear and the release ('cut-in card') to the utility. Energization depends on this release; it is on the critical path to the target milestone.
Evidence: Passed electrical final; utility release form transmitted to Dominion.
Energization / occupancyBuildingallAlways applies10LC-PERMIT-MEP
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office
2021 VUSBC, inspections
LC-PERMIT-MEP
MEP and electrical trade permits
Mechanical, electrical, plumbing and fire protection permits under the VUSBC, typically per building or per data hall. Electrical permit is the path to the utility release.
Evidence: Issued trade permits per building/phase.
Energization / occupancyBuildingallAlways applies30LC-PERMIT-SHELL
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office
2021 VUSBC, trade permits