12 public rows · 0 org rows. Public rows come only from published sources, each with its URL; rows marked Verify came through secondary reporting and must be confirmed against the primary source. Org rows are your own entries and project actuals.

12 shownAdd benchmark
MetricAssetScopeMarketItem / tradeLowMidHighUnitnAs ofSourceConfidenceNotes
Cost per WData centerAI-ready (advanced)United States—141516USD/W—2026-10-22Turner & Townsend Data Centre Construction Cost Index 2026-27Verifymost advanced AI-specific facilities. US liquid-cooled premium about 7-10% at similar IT capacity
Cost per WData centerConstruction (typical)North America——12.06—USD/W—2026-10-22Turner & Townsend Data Centre Construction Cost Index 2026-27Verify
Cost per WData centerConstruction (typical)United States——12.08—USD/W—2026-10-22Turner & Townsend Data Centre Construction Cost Index 2026-27Published62 markets, 500+ projects, typical 60 MW design
Cost per MWData centerAll-inUnited States and Canada—8.917.623.3USD M/MW—2026-01-01Cushman & Wakefield (as reported)Verifyexcludes chips and servers; up 21% since late 2024
Cost per MWData centerFit-outUnited States——2525USD M/MW—2026-01-01JLL tenant fit-out estimate (as reported)VerifyAI infrastructure fit-out upper bound
Cost per MWData centerShell and coreUnited States——12—USD M/MW—2026-01-01JLL Global Data Center Outlook 2026Verifyglobal average 11.3; 2025 10.7; 2020 7.7
Months to energizationData centerUtility interconnectUnited States primary markets—4848—months—2026-01-01JLL Global Data Center Outlook 2026Publishedaverage grid-connection wait exceeds four years
Build monthsData centerConstruction (typical)Global——18—months—2026-01-01JLL Global Data Center Outlook 2026Published50 MW facility
Lead time (weeks)Data centerProcurementUnited Statesdata center equipment, average—42—weeks—2026-01-01JLL Global Data Center Outlook 2026Verify83% above 2019; operators order up to 24 months ahead
Lead time (weeks)Data centerProcurementUnited Statesgenerator step-up transformer160160—weeks—2026-01-01Equipment lead times (VAWN)Verify143-144 weeks per Wood Mackenzie Q2 2025; over 160 weeks by Q1 2026 (industry reporting)
Lead time (weeks)Data centerProcurementUnited Statespower transformer—128—weeks—2026-01-01Equipment lead times (VAWN)Verifyabout 128 weeks per industry reporting collected in research/delay-drivers-report.md (Wood Mackenzie Q2 2025 via VAWN)
Labor rate (hourly)Data centerLaborLoudoun County, VA · VAelectrician—59.5—USD/hour base—2026-01-16Davis-Bacon VA20260200 (via aggregator)Verifyfringe 23.06; federal Davis-Bacon VA20260200 Rev 2, published 2026-01-16; confirm classification on SAM.gov

Hours-per-unit has no public rows by design: productivity benchmarks are built only from this org's project actuals and bid tabs.