PowerPMIS

Benchmarks

12 public rows · 0 org rows. Public rows come only from published sources, each with its URL; rows marked Verify came through secondary reporting and must be confirmed against the primary source. Org rows are your own entries and project actuals.

12 shownAdd benchmark
CancelPublic sources only. Never enter a client's or employer's private figures.
MetricAssetScopeMarketItem / tradeLowMidHighUnitnAs ofSourceConfidenceNotes
Cost per WData centerAI-ready (advanced)United States—141516USD/W—2026-10-22Turner & Townsend Data Centre Construction Cost Index 2026-27Verifymost advanced AI-specific facilities. US liquid-cooled premium about 7-10% at similar IT capacity
Cost per WData centerConstruction (typical)North America——12.06—USD/W—2026-10-22Turner & Townsend Data Centre Construction Cost Index 2026-27Verify
Cost per WData centerConstruction (typical)United States——12.08—USD/W—2026-10-22Turner & Townsend Data Centre Construction Cost Index 2026-27Published62 markets, 500+ projects, typical 60 MW design
Cost per MWData centerAll-inUnited States and Canada—8.917.623.3USD M/MW—2026-01-01Cushman & Wakefield (as reported)Verifyexcludes chips and servers; up 21% since late 2024
Cost per MWData centerFit-outUnited States——2525USD M/MW—2026-01-01JLL tenant fit-out estimate (as reported)VerifyAI infrastructure fit-out upper bound
Cost per MWData centerShell and coreUnited States——12—USD M/MW—2026-01-01JLL Global Data Center Outlook 2026Verifyglobal average 11.3; 2025 10.7; 2020 7.7
Months to energizationData centerUtility interconnectUnited States primary markets—4848—months—2026-01-01JLL Global Data Center Outlook 2026Publishedaverage grid-connection wait exceeds four years
Build monthsData centerConstruction (typical)Global——18—months—2026-01-01JLL Global Data Center Outlook 2026Published50 MW facility
Lead time (weeks)Data centerProcurementUnited Statesdata center equipment, average—42—weeks—2026-01-01JLL Global Data Center Outlook 2026Verify83% above 2019; operators order up to 24 months ahead
Lead time (weeks)Data centerProcurementUnited Statesgenerator step-up transformer160160—weeks—2026-01-01Equipment lead times (VAWN)Verify143-144 weeks per Wood Mackenzie Q2 2025; over 160 weeks by Q1 2026 (industry reporting)
Lead time (weeks)Data centerProcurementUnited Statespower transformer—128—weeks—2026-01-01Equipment lead times (VAWN)Verifyabout 128 weeks per industry reporting collected in research/delay-drivers-report.md (Wood Mackenzie Q2 2025 via VAWN)
Labor rate (hourly)Data centerLaborLoudoun County, VA · VAelectrician—59.5—USD/hour base—2026-01-16Davis-Bacon VA20260200 (via aggregator)Verifyfringe 23.06; federal Davis-Bacon VA20260200 Rev 2, published 2026-01-16; confirm classification on SAM.gov

Hours-per-unit has no public rows by design: productivity benchmarks are built only from this org's project actuals and bid tabs.