Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / INC-MOU
Eligibility certification and MOU with VEDP (investment and job thresholds)
Not startedlibraryProvenance
Source document
Va. Code § 58.1-609.3(18) — data center sales and use tax exemption; VEDP memorandum of understandingClause
Va. Code § 58.1-609.3(18)Trigger
Applies when an incentive program is listed for the projectDescription
Memorandum of understanding committing to the capital investment and job thresholds (commonly $150M and 50 jobs at 150% of prevailing wage; verify). The MOU fixes the performance dates and the measuring locality; sign it before equipment purchases that need the exemption.Evidence required
Executed MOU with VEDP; locality endorsement; investment and job commitment schedule.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.