Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Target energization
2029-06-30
data date 2026-11-02
Projected
2031-11-19
623 working days late
Open requirements
57
of 57
On critical path
10
Open veto points
3
Open flags
0
0 removed or consolidated
Estimate vs benchmark band
Estimate →
$1,812,000,000$12.08M/MW · band $12.08M–$12.08MWithin band+113.2% vs owner budget

What blocks energization

RequirementAuthorityOwnerStatusEarly finishFloatNext action
Entitlement · LC-PREAPP
Loudoun County, VirginiaLand-use counsel · EntitlementsNot started2026-11-300—
Entitlement · DOM-LOAD
Dominion Energy VirginiaOwner's rep · Power and utilitiesNot started2027-05-170—
Entitlement · DOM-CAPACITY
Dominion Energy VirginiaOwner's rep · Power and utilitiesNot started2027-08-090—
Entitlement · LC-SPEX
Loudoun County, VirginiaLand-use counsel · EntitlementsNot started2028-05-150—
Permit · LC-APPEAL
Loudoun County, VirginiaLand-use counsel · EntitlementsNot started2028-06-140—
Permit · LC-SITEPLAN
Loudoun County, VirginiaLand-use counsel · EntitlementsNot started2028-11-290—
Construction · DOM-CONSTRUCT
Dominion Energy VirginiaOwner's rep · Power and utilitiesNot started2029-04-040—
Construction · DOM-EQUIP
Dominion Energy VirginiaProcurement lead · Long-lead equipmentNot started2031-09-170—
Energization / occupancy · DOM-ENERGIZE
Dominion Energy VirginiaOwner's rep · Power and utilitiesNot started2031-10-290—
Energization / occupancy · LC-CO
Loudoun County, VirginiaPermit expediter · Building permits and inspectionsNot started2031-11-190—

Open flags

No open duplicates, conflicts or gaps.