PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / DOM-CAPACITY

Capacity confirmation letter with energization date

Not startedVetolibrary

Provenance

Source document
Dominion Energy Virginia large-load interconnection process and terms and conditions of service
Clause
not stated
Trigger
Applies at 25 MW peak load or more
Description
Written confirmation of deliverable capacity and a target energization date, by phase. Some Virginia localities (York County, Jun 2025) require a capacity letter as a condition of zoning; Loudoun does not formally, but the Board expects it. If the date lands past the project target this is a project veto.
Evidence required
Dominion capacity letter stating MW by phase and estimated energization dates.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (3)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete