Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-CAPACITY
Capacity confirmation letter with energization date
Not startedVetolibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia large-load interconnection process and terms and conditions of serviceClause
not statedTrigger
Applies at 25 MW peak load or moreDescription
Written confirmation of deliverable capacity and a target energization date, by phase. Some Virginia localities (York County, Jun 2025) require a capacity letter as a condition of zoning; Loudoun does not formally, but the Board expects it. If the date lands past the project target this is a project veto.Evidence required
Dominion capacity letter stating MW by phase and estimated energization dates.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Large-load study request (interconnection request) Not started FS
Waits on this (3)
Schedule activity
Delete