PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / DOM-GS5

GS-5 large-load contract execution (14-year term, minimum demand charges)

Not startedlibrary

Provenance

Clause
Schedule GS-5 (SCC final order, Nov 25, 2025)
Trigger
Applies at 25 MW peak load or more (GS-5 threshold)
Description
Execution of the Schedule GS-5 electric service agreement: 14-year contract, 85% transmission & distribution and 60% generation minimum demand charges, effective for service from Jan 1, 2027. Take-or-pay exposure sits with the owner until the tenant lease backs it.
Evidence required
Fully executed GS-5 service agreement; counsel summary of minimum-bill and exit terms.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (2)
Waits on this (3)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete

Delete requirementPrefer marking it waived or N/A so the register keeps the record.