Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-GS5
GS-5 large-load contract execution (14-year term, minimum demand charges)
Not startedlibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia Schedule GS-5 (large general service, 25 MW+) — SCC final order in the 2025 biennial review · SCC order Nov 25, 2025 · effective 2027-01-01Clause
Schedule GS-5 (SCC final order, Nov 25, 2025)Trigger
Applies at 25 MW peak load or more (GS-5 threshold)Description
Execution of the Schedule GS-5 electric service agreement: 14-year contract, 85% transmission & distribution and 60% generation minimum demand charges, effective for service from Jan 1, 2027. Take-or-pay exposure sits with the owner until the tenant lease backs it.Evidence required
Fully executed GS-5 service agreement; counsel summary of minimum-bill and exit terms.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (2)
- Capacity confirmation letter with energization date Not started FS
- Special exception / rezoning approval (data center use) Not started FS
Waits on this (3)
Schedule activity