Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-CONSTRUCT
Construction / line extension and substation agreement
Not startedlibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia large-load interconnection process and terms and conditions of serviceClause
not statedTrigger
Applies at 25 MW peak load or moreDescription
Agreement covering the utility-side facilities (transmission tap, substation, feeders), customer contribution in aid of construction, easements and the utility's construction schedule. Dominion will not finalize substation design until tariff, collateral and site control are firm.Evidence required
Executed construction agreement; recorded easements; CIAC payment receipt; utility schedule.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (2)
- GS-5 large-load contract execution (14-year term, minimum demand charges) Not started FS
- Site plan (STPL) approval Not started FS
Waits on this (3)
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.