Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-ENERGIZE
Energization prerequisites
Not startedlibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia large-load interconnection process and terms and conditions of serviceClause
not statedTrigger
Always appliesDescription
Checklist Dominion requires before closing the breaker: contract in force, collateral posted, utility facilities complete and tested, metering installed, county electrical release received, customer protection settings accepted.Evidence required
Dominion energization checklist signed off; meter set; energization date confirmation.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (4)
- Collateral posting (reported ~$1.5M per MW) Not started FS
- Construction / line extension and substation agreement Not started FS
- Long-lead utility equipment release (power transformers ~128 weeks, GSUs 160+ weeks) Not started FS
- Electrical final inspection and utility release Not started FS
Waits on this (1)
- Certificate of occupancy by phase / data hall Not started