PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / DOM-ENERGIZE

Energization prerequisites

Not startedlibrary

Provenance

Source document
Dominion Energy Virginia large-load interconnection process and terms and conditions of service
Clause
not stated
Trigger
Always applies
Description
Checklist Dominion requires before closing the breaker: contract in force, collateral posted, utility facilities complete and tested, metering installed, county electrical release received, customer protection settings accepted.
Evidence required
Dominion energization checklist signed off; meter set; energization date confirmation.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (4)
Waits on this (1)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete