Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LC-SITEPLAN
Site plan (STPL) approval
Not startedlibraryProvenance
Authority
Loudoun County, VirginiaSource document
Loudoun County Land Subdivision and Development Ordinance (LSDO)Clause
Loudoun LSDO, site plan review procedure; FSM design standardsTrigger
Always appliesDescription
Engineering site plan reviewed against the FSM and LSDO and the entitlement conditions: grading, utilities, stormwater concept, access, landscaping and lighting. Multiple review cycles are normal; each cycle is a re-submission. The Section 404 determination should be in hand so the limits of disturbance are final.Evidence required
Approved and signed site plan set; condition compliance matrix; bond/agreement executed.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (3)
- Special exception / rezoning approval (data center use) Not started FS
- Appeal period expiry on entitlement approval Not started FS
- Section 404 nationwide permit verification (impacts up to 0.5 acre) Not started FS
Waits on this (5)
- Stormwater management plan approval (VSMP authority) Not started
- Erosion and sediment control plan approval Not started
- Fire marshal plan review: lithium-ion UPS (NFPA 855), bulk diesel (NFPA 30), responder access Not started
- Construction / line extension and substation agreement Not started
- Third-party reports: appraisal, Phase I ESA, geotechnical, ALTA survey Not started
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.