Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / FED-404-NWP

Section 404 nationwide permit verification (impacts up to 0.5 acre)

Not startedlibrary

Provenance

Clause
2026 Nationwide Permit reissuance (Federal Register, Jan 8, 2026)
Trigger
Applies when Section 404 impacts are above 0 and at or below 0.5 acre
Description
Verification under a nationwide permit (e.g. NWP 39 commercial development) for impacts at or below the 0.5-acre threshold. FY2024 average 55 calendar days per the 2026 NWP rule; 4–7 months in practice. Designing under NWP thresholds is one of the highest-leverage schedule decisions on the project.
Evidence required
Corps NWP verification letter with conditions; mitigation credit purchase if required.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (1)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete