Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / FED-404-DELIN
Wetland delineation and jurisdictional determination
Not startedlibraryProvenance
Authority
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)Source document
USACE Reissuance and Modification of Nationwide Permits (2026 NWP rule) · effective 2026-01-08Clause
not statedTrigger
Applies when wetlands or streams are present on the siteDescription
Field delineation of waters of the United States and a Corps jurisdictional determination (approved or preliminary). Sets the impact acreage that decides the 404 pathway; do it before the site plan so the layout can be designed under nationwide permit thresholds.Evidence required
Delineation report; Corps JD letter; impact acreage table by alternative.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.