PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Clear
17 shown · 57 open of 57
Add requirement
CSV
CodeRequirementAuthoritySource / clauseTriggerOwnerStatusDueDaysVeto
DEQ-AIR-PRECONPre-permit construction limits confirmed (DEQ Clarification 2025-03)
Construction · Air
Virginia Department of Environmental Quality
DEQ Clarification 2025-03: construction activities permitted before air permit issuance
—
Applies when generators are proposed (generator count >= 1)Environmental consultant
—5
DEQ-VPDES-CGPVPDES construction stormwater general permit coverage (SWPPP)
Construction · Stormwater
Virginia Department of Environmental Quality
VPDES General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880)
9VAC25-880 (construction general permit)
Applies when land disturbance is one acre or more (site acreage >= 1)Civil engineer
—15
DEQ-VSMPPost-construction stormwater compliance (nutrient credits / BMP maintenance)
Construction · Stormwater
Virginia Department of Environmental Quality
VPDES General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880)
Virginia Stormwater Management Program Regulation (9VAC25-870), water quality criteria
Applies when land disturbance is one acre or more (site acreage >= 1)Civil engineer
—20
DOM-COLLATERALCollateral posting (reported ~$1.5M per MW)
Construction · Utility
Dominion Energy Virginia
Dominion Energy Virginia Schedule GS-5 (large general service, 25 MW+) — SCC final order in the 2025 biennial review (SCC order Nov 25, 2025)
Schedule GS-5, security/collateral provisions
Applies at 25 MW peak load or moreOwner's rep
—20
DOM-CONSTRUCTConstruction / line extension and substation agreement
Construction · Utility
Dominion Energy Virginia
Dominion Energy Virginia large-load interconnection process and terms and conditions of service
—
Applies at 25 MW peak load or moreOwner's rep
—90
DOM-EQUIPLong-lead utility equipment release (power transformers ~128 weeks, GSUs 160+ weeks)
Construction · Procurement
Dominion Energy Virginia
Dominion Energy Virginia large-load interconnection process and terms and conditions of service
—
Applies at 25 MW peak load or more (dedicated substation equipment)Procurement lead
—640
DOM-GS5GS-5 large-load contract execution (14-year term, minimum demand charges)
Construction · Utility
Dominion Energy Virginia
Dominion Energy Virginia Schedule GS-5 (large general service, 25 MW+) — SCC final order in the 2025 biennial review (SCC order Nov 25, 2025)
Schedule GS-5 (SCC final order, Nov 25, 2025)
Applies at 25 MW peak load or more (GS-5 threshold)Owner's rep
—90
INC-CERTExemption certificate from the Department of Taxation
Construction · Incentive
Virginia data center retail sales and use tax exemption
Va. Code § 58.1-609.3(18) — data center sales and use tax exemption; VEDP memorandum of understanding
—
Applies when an incentive program is listed for the projectTax counsel
—20
LC-FIRE-REVIEWFire marshal plan review: lithium-ion UPS (NFPA 855), bulk diesel (NFPA 30), responder access
Construction · Fire
Loudoun County, Virginia
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office (2021 VUSBC / 2021 SFPC)
2021 SFPC / VUSBC; NFPA 855; NFPA 30; IFC Ch. 12
Applies when generators with on-site diesel storage are proposed (generator count >= 1); battery MWh is reviewed in the same packageFire protection engineer
—40
LC-PERMIT-FOUNDFoundation (early-start) building permit
Construction · Building
Loudoun County, Virginia
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office (2021 VUSBC / 2021 SFPC)
2021 VUSBC, phased/partial permits
Always appliesPermit expediter
—30
LC-PERMIT-GRADINGGrading / land disturbance permit
Construction · Building
Loudoun County, Virginia
Loudoun County Land Subdivision and Development Ordinance (LSDO)
Loudoun LSDO / FSM, land disturbance permit
Always appliesPermit expediter
—20
LC-PERMIT-SHELLBuilding shell permit
Construction · Building
Loudoun County, Virginia
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office (2021 VUSBC / 2021 SFPC)
2021 VUSBC, permit application and plan review
Always appliesPermit expediter
—45
LEN-CLOSELoan closing
Construction · Lender
Construction lender (template conditions)
Construction loan agreement template — conditions precedent, draw conditions, covenants
Loan agreement, closing
Applies when a construction lender is namedProject finance lead
—15
LEN-DRAWDraw conditions and covenant reporting
Construction · Lender
Construction lender (template conditions)
Construction loan agreement template — conditions precedent, draw conditions, covenants
Loan agreement, conditions to each advance; reporting covenants
Applies when a construction lender is namedProject finance lead
—10
LEN-IASigned utility interconnection / service agreement before first draw
Construction · Lender
Construction lender (template conditions)
Construction loan agreement template — conditions precedent, draw conditions, covenants
Loan agreement, conditions precedent to first advance (utility agreements)
Applies when a construction lender is namedProject finance lead
—5
TEN-CHANGEChange-order impact review across permits (change-impact protocol)
Construction · Tenant
Hyperscale tenant specification (template)
Lease / build-to-suit agreement — delivery milestones and liquidated damages (template)
—
Applies when a tenant is namedDevelopment director
—10
TEN-MILESTONESDelivery milestones and liquidated damages schedule
Construction · Tenant
Hyperscale tenant specification (template)
Lease / build-to-suit agreement — delivery milestones and liquidated damages (template)
—
Applies when a tenant is namedDevelopment director
—15

Gate: Before entitlement filing → Before permit application → Before construction start → Before energization / occupancy.