Building shell permit
Not startedlibraryProvenance
Authority
Loudoun County, VirginiaSource document
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office · 2021 VUSBC / 2021 SFPC · effective 2024-01-18Clause
2021 VUSBC, permit application and plan reviewTrigger
Always appliesDescription
Full building permit for the shell. For generator fleets, VA DEQ Clarification 2025-03 limits what may be built before the air permit issues, so the air permit is a predecessor here. Fire marshal review of the generator yard, diesel storage and ESS must be complete.Evidence required
Issued building permit; approved plan set; fire marshal approval letter.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (3)
- Foundation (early-start) building permit Not started FS
- Fire marshal plan review: lithium-ion UPS (NFPA 855), bulk diesel (NFPA 30), responder access Not started FS
- Air permit — state major NSR plus Title V operating permit Not started FS
Waits on this (1)
- MEP and electrical trade permits Not started
Schedule activity
Delete