Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / DEQ-VSMP

Post-construction stormwater compliance (nutrient credits / BMP maintenance)

Not startedlibrary

Provenance

Source document
VPDES General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880)
Clause
Virginia Stormwater Management Program Regulation (9VAC25-870), water quality criteria
Trigger
Applies when land disturbance is one acre or more (site acreage >= 1)
Description
VSMP water-quality compliance for the built condition: on-site BMPs plus purchase of nutrient credits for any remaining phosphorus load, and the recorded BMP maintenance agreement. Often resolved at the last minute before the grading permit; schedule it with the SWM plan.
Evidence required
Nutrient credit purchase certificate; recorded maintenance agreement.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (0)
  • None — feeds the target directly.

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete

Delete requirementPrefer marking it waived or N/A so the register keeps the record.