Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DEQ-VSMP
Post-construction stormwater compliance (nutrient credits / BMP maintenance)
Not startedlibraryProvenance
Source document
VPDES General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880)Clause
Virginia Stormwater Management Program Regulation (9VAC25-870), water quality criteriaTrigger
Applies when land disturbance is one acre or more (site acreage >= 1)Description
VSMP water-quality compliance for the built condition: on-site BMPs plus purchase of nutrient credits for any remaining phosphorus load, and the recorded BMP maintenance agreement. Often resolved at the last minute before the grading permit; schedule it with the SWM plan.Evidence required
Nutrient credit purchase certificate; recorded maintenance agreement.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Stormwater management plan approval (VSMP authority) Not started FS
Waits on this (0)
- None — feeds the target directly.