Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / LEN-CLOSE

Loan closing

Not startedlibrary

Provenance

Source document
Construction loan agreement template — conditions precedent, draw conditions, covenants
Clause
Loan agreement, closing
Trigger
Applies when a construction lender is named
Description
Closing of the construction loan once all conditions precedent are met: entitlements final, reports accepted, executed tenant lease, GMP contract, title and insurance in place.
Evidence required
Executed loan documents; closing statement; title policy.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (3)
Waits on this (2)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete