Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LEN-CLOSE
Loan closing
Not startedlibraryProvenance
Source document
Construction loan agreement template — conditions precedent, draw conditions, covenantsClause
Loan agreement, closingTrigger
Applies when a construction lender is namedDescription
Closing of the construction loan once all conditions precedent are met: entitlements final, reports accepted, executed tenant lease, GMP contract, title and insurance in place.Evidence required
Executed loan documents; closing statement; title policy.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (3)
- Condition precedent: entitlements final and appeal period expired Not started FS
- Third-party reports: appraisal, Phase I ESA, geotechnical, ALTA survey Not started FS
- Lease execution and commencement conditions Not started FS
Waits on this (2)