Data center · Loudoun County, VA · target energization 2029-06-30
Clear
18 shown · 57 open of 57
Add requirement
CSV
CodeRequirementAuthoritySource / clauseTriggerOwnerStatusDueDaysVeto
DEQ-AIR-MAJORAir permit — state major NSR plus Title V operating permit
Permit · Air
Virginia Department of Environmental Quality
Virginia Air Permit Regulations for Stationary Sources (9VAC5-80): minor NSR, state major NSR, PSD and Title V
9VAC5-80 (state major NSR; Title V operating permits)
Applies to mid-size fleets (21–80 generators; proxy threshold, estimate)Environmental consultant
—190
DEQ-TIER4Tier 4 generator requirement (applications on or after July 1, 2026)
Permit · Air
Virginia Department of Environmental Quality
Virginia HB 507 (2024) data center generator emissions — Va. Code § 10.1-1322.6
Va. Code § 10.1-1322.6; DEQ APG-576 (Apr 9, 2026)
Applies when generators are proposed (generator count >= 1); application date on/after 2026-07-01Environmental consultant
—10
DEQ-VWPVirginia Water Protection (VWP) permit for wetland and stream impacts
Permit · Water
Virginia Department of Environmental Quality
DEQ water permitting: Virginia Water Protection (VWP) permit program and water withdrawal permitting
—
Applies when wetlands are present on the siteCivil engineer
—120
DEQ-WATER-DISCHARGECooling water discharge authorization (VPDES or sewer-authority pretreatment)
Permit · Water
Virginia Department of Environmental Quality
DEQ water permitting: Virginia Water Protection (VWP) permit program and water withdrawal permitting
—
Applies when a process/cooling discharge is proposed (discharge gpd > 0)Civil engineer
—90
DEQ-WATER-WITHDRAWWater withdrawal permit / supply confirmation for cooling
Permit · Water
Virginia Department of Environmental Quality
DEQ water permitting: Virginia Water Protection (VWP) permit program and water withdrawal permitting
—
Applies to large withdrawals (>= 300,000 gallons/day; planning threshold, estimate)Civil engineer
—180
FED-106Section 106 historic resources consultation
Permit · Environmental
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)
National Historic Preservation Act Section 106 regulations (36 CFR Part 800)
36 CFR Part 800
Applies when the site is near historic or cultural resources (and a federal nexus exists)Environmental consultant
—90
FED-404-NWPSection 404 nationwide permit verification (impacts up to 0.5 acre)
Permit · Federal
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)
USACE Reissuance and Modification of Nationwide Permits (2026 NWP rule)
2026 Nationwide Permit reissuance (Federal Register, Jan 8, 2026)
Applies when Section 404 impacts are above 0 and at or below 0.5 acreEnvironmental consultant
—40
FED-FAA-7460FAA Form 7460-1 determination (airport proximity)
Permit · Federal
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)
FAA Form 7460-1 Notice of Proposed Construction or Alteration (14 CFR Part 77)
14 CFR Part 77, notice criteria
Applies within 5 miles of an airport (conservative screen for the Part 77 notice surface)Environmental consultant
—45
FED-NEPA-REVIEWNEPA documentation for the federal action (CatEx / EA / EIS)
Permit · Federal
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)
National Environmental Policy Act as amended by the Fiscal Responsibility Act of 2023; CEQ EIS Timeline Report (Jan 2025)
—
Applies when a federal permit (e.g. Corps 404) is requiredEnvironmental consultant
—120
LC-APPEALAppeal period expiry on entitlement approval
Permit · Zoning
Loudoun County, Virginia
Virginia public hearing advertisement and notice requirements for zoning actions (Va. Code § 15.2-2204) and Loudoun hearing calendar
—
Always appliesLand-use counsel
—22
LC-ESCErosion and sediment control plan approval
Permit · Stormwater
Loudoun County, Virginia
Loudoun County Facilities Standards Manual (FSM)
Virginia Erosion and Sediment Control Regulations (9VAC25-840); Loudoun FSM
Always appliesCivil engineer
—30
LC-SITEPLANSite plan (STPL) approval
Permit · Zoning
Loudoun County, Virginia
Loudoun County Land Subdivision and Development Ordinance (LSDO)
Loudoun LSDO, site plan review procedure; FSM design standards
Always appliesLand-use counsel
—120
LC-SWMStormwater management plan approval (VSMP authority)
Permit · Stormwater
Loudoun County, Virginia
Loudoun County Facilities Standards Manual (FSM)
Loudoun FSM stormwater chapter; Virginia Stormwater Management Program Regulation (9VAC25-870)
Applies when land disturbance is one acre or more (site acreage >= 1)Civil engineer
—45
LEN-CP-ENTITLECondition precedent: entitlements final and appeal period expired
Permit · Lender
Construction lender (template conditions)
Construction loan agreement template — conditions precedent, draw conditions, covenants
Loan agreement, conditions precedent to closing (entitlements)
Applies when a construction lender is namedProject finance lead
—10
LEN-REPORTSThird-party reports: appraisal, Phase I ESA, geotechnical, ALTA survey
Permit · Lender
Construction lender (template conditions)
Construction loan agreement template — conditions precedent, draw conditions, covenants
Loan agreement, conditions precedent to closing (reports)
Applies when a construction lender is namedProject finance lead
—60
PJM-BYONGBring-your-own-generation / Connect-and-Manage election
Permit · Utility
PJM Interconnection (regional transmission organization)
PJM Board letter on the results of the CIFP process for large load additions
—
Applies at 50 MW or moreOwner's rep
—40
PJM-CAPACITYCapacity cost and curtailment exposure assessment
Permit · Utility
PJM Interconnection (regional transmission organization)
PJM 2026/2027 Base Residual Auction report (and 2027/28, 2028/29 results)
—
Applies at 50 MW or moreOwner's rep
—20
TEN-LEASELease execution and commencement conditions
Permit · Tenant
Hyperscale tenant specification (template)
Lease / build-to-suit agreement — delivery milestones and liquidated damages (template)
—
Applies when a tenant is namedDevelopment director
—30