Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DEQ-WATER-WITHDRAW
Water withdrawal permit / supply confirmation for cooling
Not startedlibraryProvenance
Source document
DEQ water permitting: Virginia Water Protection (VWP) permit program and water withdrawal permittingClause
not statedTrigger
Applies to large withdrawals (>= 300,000 gallons/day; planning threshold, estimate)Description
Confirmation that the cooling water supply is permitted: DEQ withdrawal permit for surface or groundwater sources, or a capacity commitment letter from the municipal supplier. The 300,000 gpd trigger is a planning threshold, not a regulatory one. Water is a political gate in the arid West and an opposition theme in Virginia.Evidence required
DEQ withdrawal permit or municipal supplier capacity/availability letter sized to peak day demand.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.