Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DEQ-WATER-DISCHARGE
Cooling water discharge authorization (VPDES or sewer-authority pretreatment)
Not startedlibraryProvenance
Source document
DEQ water permitting: Virginia Water Protection (VWP) permit program and water withdrawal permittingClause
not statedTrigger
Applies when a process/cooling discharge is proposed (discharge gpd > 0)Description
Authorization for cooling tower blowdown and process discharge: VPDES individual permit if to surface water, or an industrial pretreatment/discharge permit from the sewer authority if to sanitary sewer.Evidence required
VPDES permit or sewer authority discharge permit with limits.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Water withdrawal permit / supply confirmation for cooling Not started FS
Waits on this (0)
- None — feeds the target directly.
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.