PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / DEQ-WATER-DISCHARGE

Cooling water discharge authorization (VPDES or sewer-authority pretreatment)

Not startedlibrary

Provenance

Source document
DEQ water permitting: Virginia Water Protection (VWP) permit program and water withdrawal permitting
Clause
not stated
Trigger
Applies when a process/cooling discharge is proposed (discharge gpd > 0)
Description
Authorization for cooling tower blowdown and process discharge: VPDES individual permit if to surface water, or an industrial pretreatment/discharge permit from the sewer authority if to sanitary sewer.
Evidence required
VPDES permit or sewer authority discharge permit with limits.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (0)
  • None — feeds the target directly.

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete