Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / DEQ-TIER4

Tier 4 generator requirement (applications on or after July 1, 2026)

Not startedlibrary

Provenance

Clause
Va. Code § 10.1-1322.6; DEQ APG-576 (Apr 9, 2026)
Trigger
Applies when generators are proposed (generator count >= 1); application date on/after 2026-07-01
Description
Va. Code § 10.1-1322.6 (HB 507) requires Tier 4 or equivalent emission performance for data center generator permit applications received on or after July 1, 2026; DEQ APG-576 sets a presumptive NOx limit of 0.60 g/hp-hr. Confirm the procured units meet it before the application is filed; a non-Tier 4 spec is a re-design.
Evidence required
Manufacturer emission certification (Tier 4 / 0.60 g/hp-hr NOx) for the specified units.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (1)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete

Delete requirementPrefer marking it waived or N/A so the register keeps the record.