Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DEQ-AIR-SCREEN
Generator fleet emissions inventory and permit pathway determination
Not startedlibraryProvenance
Source document
Virginia Air Permit Regulations for Stationary Sources (9VAC5-80): minor NSR, state major NSR, PSD and Title VClause
not statedTrigger
Applies when generators are proposed (generator count >= 1)Description
Potential-to-emit calculation for the proposed generator fleet (count, kW, tier, hours) to pick the permit pathway: synthetic minor, state major + Title V, or PSD. This is the single highest-leverage air decision; the fleet spec from the tenant must be frozen first.Evidence required
Emissions inventory spreadsheet; pathway memo from the air consultant; DEQ pre-application meeting notes.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Generator, density and redundancy specification lock Not started FS
Waits on this (3)
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.