Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / PJM-BYONG
Bring-your-own-generation / Connect-and-Manage election
Not startedlibraryProvenance
Source document
PJM Board letter on the results of the CIFP process for large load additions · effective 2026-01-16Clause
not statedTrigger
Applies at 50 MW or moreDescription
Decision on whether to pair the load with new generation (BYONG) or accept Connect-and-Manage curtailable service under the PJM large-load framework and the FERC co-location order. On-site generation adds air permits and pipeline approvals (turbines 3–7 years for some units).Evidence required
Signed election memo; if BYONG, generation interconnection request number.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Capacity cost and curtailment exposure assessment Not started FS
Waits on this (0)
- None — feeds the target directly.
Schedule activity
Delete