Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / PJM-BYONG

Bring-your-own-generation / Connect-and-Manage election

Not startedlibrary

Provenance

Clause
not stated
Trigger
Applies at 50 MW or more
Description
Decision on whether to pair the load with new generation (BYONG) or accept Connect-and-Manage curtailable service under the PJM large-load framework and the FERC co-location order. On-site generation adds air permits and pipeline approvals (turbines 3–7 years for some units).
Evidence required
Signed election memo; if BYONG, generation interconnection request number.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (0)
  • None — feeds the target directly.

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.