Data center · Loudoun County, VA · target energization 2029-06-30Register / PJM-CAPACITY
Capacity cost and curtailment exposure assessment
Not startedlibraryProvenance
Clause
not statedTrigger
Applies at 50 MW or moreDescription
Owner/tenant assessment of capacity price exposure ($333.44/MW-day cap for 2027/28; 6,623 MW short) and of any curtailment or interruptibility conditions attached to the service. Feeds the lease's pass-through terms and the lender's underwriting.Evidence required
Exposure memo with capacity price scenarios and curtailment terms, accepted by the tenant and lender.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- PJM large-load visibility and transmission study awareness Not started FS
Waits on this (1)
Schedule activity