PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / PJM-CAPACITY

Capacity cost and curtailment exposure assessment

Not startedlibrary

Provenance

Clause
not stated
Trigger
Applies at 50 MW or more
Description
Owner/tenant assessment of capacity price exposure ($333.44/MW-day cap for 2027/28; 6,623 MW short) and of any curtailment or interruptibility conditions attached to the service. Feeds the lease's pass-through terms and the lender's underwriting.
Evidence required
Exposure memo with capacity price scenarios and curtailment terms, accepted by the tenant and lender.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (1)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete

Delete requirementPrefer marking it waived or N/A so the register keeps the record.