Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / PJM-LARGELOAD
PJM large-load visibility and transmission study awareness
Not startedlibraryProvenance
Source document
PJM Board letter on the results of the CIFP process for large load additions · effective 2026-01-16Clause
not statedTrigger
Applies at 50 MW or more (PJM large-load definition)Description
Confirm with Dominion that the load is included in PJM's load forecast and transmission planning (loads at 50 MW and above are 'large loads' under the Jan 2026 Board decision). A load needing new transmission faces 24–48+ months (CBRE); knowing early whether the Dominion capacity letter depends on a PJM transmission upgrade is the point of this item.Evidence required
Dominion confirmation of inclusion in the PJM load forecast; list of any required transmission upgrades with RTEP status.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Large-load study request (interconnection request) Not started FS
Waits on this (1)
Schedule activity
Delete
Delete requirementPrefer marking it waived or N/A so the register keeps the record.