Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / PJM-LARGELOAD

PJM large-load visibility and transmission study awareness

Not startedlibrary

Provenance

Clause
not stated
Trigger
Applies at 50 MW or more (PJM large-load definition)
Description
Confirm with Dominion that the load is included in PJM's load forecast and transmission planning (loads at 50 MW and above are 'large loads' under the Jan 2026 Board decision). A load needing new transmission faces 24–48+ months (CBRE); knowing early whether the Dominion capacity letter depends on a PJM transmission upgrade is the point of this item.
Evidence required
Dominion confirmation of inclusion in the PJM load forecast; list of any required transmission upgrades with RTEP status.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (1)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.