Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / FED-NEPA-SCREEN
NEPA / federal nexus screen
Not startedlibraryProvenance
Authority
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)Source document
National Environmental Policy Act as amended by the Fiscal Responsibility Act of 2023; CEQ EIS Timeline Report (Jan 2025)Clause
not statedTrigger
Always appliesDescription
Intake screen for any federal nexus: federal land, funding, loan guarantee or permit (including the Corps 404 action). Also flags CFIUS/export-control questions for a parallel track. Universal because the trigger model cannot express 'any federal input is true'; the review itself is keyed to the permit input.Evidence required
Nexus screening memo signed by counsel listing each federal touchpoint and the responsible agency.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Pre-application meeting with Planning & Zoning Not started FS
Waits on this (3)
- NEPA documentation for the federal action (CatEx / EA / EIS) Not started
- FAST-41 / EO 14318 coverage eligibility Not started
- Section 106 historic resources consultation Not started