NEPA documentation for the federal action (CatEx / EA / EIS)

Not startedlibrary

Provenance

Clause
not stated
Trigger
Applies when a federal permit (e.g. Corps 404) is required
Description
Agency NEPA review tied to the federal permit. Nationwide permit verifications are covered programmatically; an individual permit normally needs an EA. Duration shown is an EA estimate; an EIS ran a median 2.2 years NOI to final for 2024 (CEQ) with only 39% inside the two-year statutory deadline.
Evidence required
CatEx determination, FONSI or ROD from the lead agency.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (0)
  • None — feeds the target directly.

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.