Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / FED-FAST41
FAST-41 / EO 14318 coverage eligibility
Not startedlibraryProvenance
Authority
US Army Corps of Engineers and federal nexus agencies (NEPA, FAA, SHPO, Permitting Council)Source document
FAST-41 (Title 41 of the FAST Act) and Executive Order 14318 on accelerating federal permitting of data center infrastructure · effective 2025-07-23Clause
not statedTrigger
Applies at 100 MW or more (EO 14318 threshold for AI data centers)Description
Screen for FAST-41 coverage under Executive Order 14318 (AI data centers over 100 MW), which puts all federal authorizations on a single Permitting Dashboard timetable. FAST-41 cut EIS timelines 45% in FY2020 (FPISC); the first data center was covered Apr 2, 2026. Only useful where a federal nexus exists.Evidence required
FAST-41 initiation notice filed, or memo documenting why coverage was not sought.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- NEPA / federal nexus screen Not started FS
Waits on this (0)
- None — feeds the target directly.