Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LEN-CP-ENTITLE
Condition precedent: entitlements final and appeal period expired
Not startedlibraryProvenance
Source document
Construction loan agreement template — conditions precedent, draw conditions, covenantsClause
Loan agreement, conditions precedent to closing (entitlements)Trigger
Applies when a construction lender is namedDescription
Lender will not close until the special exception/rezoning and site plan approvals are final and non-appealable and all conditions capable of satisfaction before closing are satisfied.Evidence required
Zoning counsel opinion; certified approval resolution; appeal period confirmation.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (2)
- Special exception / rezoning approval (data center use) Not started FS
- Appeal period expiry on entitlement approval Not started FS
Waits on this (1)
- Loan closing Not started