Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DEQ-AIR-PRECON
Pre-permit construction limits confirmed (DEQ Clarification 2025-03)
Not startedlibraryProvenance
Source document
DEQ Clarification 2025-03: construction activities permitted before air permit issuanceClause
not statedTrigger
Applies when generators are proposed (generator count >= 1)Description
Written confirmation from DEQ or the air consultant of which construction activities may proceed before the air permit issues (site work and shell generally yes; generator pads, fuel systems and exhaust no). Protects the grading/foundation early start from an enforcement problem.Evidence required
Consultant/DEQ memo listing permitted pre-issuance activities, filed with the grading permit.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
Waits on this (0)
- None — feeds the target directly.