PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
Register / LC-NOISE

Noise study (generator and mechanical plant)

Not startedlibrary

Provenance

Source document
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination) · 2023 ZO, 2025 data center amendment · effective 2025-03-12
Clause
Loudoun Zoning Ordinance, performance standards (noise)
Trigger
Applies when standby generators are proposed (generator count >= 1)
Description
Acoustic study of standby generator testing and cooling plant against the county noise standards. Noise is a recurring opposition theme and a redesign-and-re-review driver; the study is typically a condition of the special exception and is re-run if the generator or cooling spec changes.
Evidence required
Acoustic report with modeled property-line levels; mitigation design if limits are exceeded.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (2)
Waits on this (1)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.

Delete