Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LC-INSPECT-ELEC
Electrical final inspection and utility release
Not startedlibraryProvenance
Authority
Loudoun County, VirginiaSource document
Virginia Uniform Statewide Building Code (2021 edition) and Statewide Fire Prevention Code (2021), as enforced by Loudoun Building and Development and the Fire Marshal's Office · 2021 VUSBC / 2021 SFPC · effective 2024-01-18Clause
2021 VUSBC, inspectionsTrigger
Always appliesDescription
County electrical inspection of the service entrance and switchgear and the release ('cut-in card') to the utility. Energization depends on this release; it is on the critical path to the target milestone.Evidence required
Passed electrical final; utility release form transmitted to Dominion.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- MEP and electrical trade permits Not started FS
Waits on this (2)
- Certificate of occupancy by phase / data hall Not started
- Energization prerequisites Not started