Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LC-APPEAL
Appeal period expiry on entitlement approval
Not startedlibraryProvenance
Authority
Loudoun County, VirginiaSource document
Virginia public hearing advertisement and notice requirements for zoning actions (Va. Code § 15.2-2204) and Loudoun hearing calendarClause
not statedTrigger
Always appliesDescription
Statutory window for a challenge to the legislative approval to be filed. Lenders and most counterparties will not close until the approval is final and non-appealable. Virginia's window is commonly 30 calendar days from the decision; confirm with counsel for the specific action. Universal class.Evidence required
Counsel letter confirming the appeal period has run with no filing (docket search attached).Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Special exception / rezoning approval (data center use) Not started FS
Waits on this (2)
- Site plan (STPL) approval Not started
- Condition precedent: entitlements final and appeal period expired Not started