Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LEN-IA
Signed utility interconnection / service agreement before first draw
Not startedlibraryProvenance
Source document
Construction loan agreement template — conditions precedent, draw conditions, covenantsClause
Loan agreement, conditions precedent to first advance (utility agreements)Trigger
Applies when a construction lender is namedDescription
Lender requires the executed Dominion GS-5 agreement and construction agreement (and the capacity letter) before advancing construction funds, because the project has no value without an energization date. Collateral posting under GS-5 is usually funded from equity, not the loan.Evidence required
Executed GS-5 and construction agreements delivered to the lender; lender acknowledgement.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (3)
- GS-5 large-load contract execution (14-year term, minimum demand charges) Not started FS
- Construction / line extension and substation agreement Not started FS
- Loan closing Not started FS
Waits on this (1)
- Draw conditions and covenant reporting Not started