Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LC-PREAPP
Pre-application meeting with Planning & Zoning
Not startedlibraryProvenance
Authority
Loudoun County, VirginiaSource document
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination) · 2023 ZO, 2025 data center amendment · effective 2025-03-12Clause
Loudoun Zoning Ordinance, application procedures (pre-application conference)Trigger
Always appliesDescription
Required pre-application conference with county staff before a special exception, rezoning or site plan filing. Establishes the application type, required studies (traffic, noise, fiscal) and the hearing track. Loudoun's process is the start of the statutory clock; nothing else files before it.Evidence required
Pre-application meeting notes from county staff listing required submittals and studies.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (0)
- None — starts at the data date.
Waits on this (10)
- Notice and hearing compliance plan Not started
- Traffic impact study Not started
- Noise study (generator and mechanical plant) Not started
- Special exception / rezoning approval (data center use) Not started
- Owner pushback / waiver decision log Not started
- Large-load study request (interconnection request) Not started
- Water withdrawal permit / supply confirmation for cooling Not started
- Wetland delineation and jurisdictional determination Not started
- NEPA / federal nexus screen Not started
- Eligibility certification and MOU with VEDP (investment and job thresholds) Not started