Data center · Loudoun County, VA · target energization 2029-06-30
Register / DOM-LOAD

Large-load study request (interconnection request)

Not startedlibrary

Provenance

Source document
Dominion Energy Virginia large-load interconnection process and terms and conditions of service
Clause
not stated
Trigger
Applies at 25 MW peak load or more (GS-5 large-load threshold)
Description
Formal request for Dominion to study serving the campus load: site, phasing, peak and connected MW, in-service dates. Utilities generally require site control before studying; some require zoning. Duration is for the study itself; queue position can add years and is tracked on the capacity letter class.
Evidence required
Submitted load study request with Dominion acknowledgement and queue/reference number; study fee receipt.

Edit

Evidence (0)

Nothing attached. A requirement is only satisfied with evidence.

Dependencies

Must finish first (1)
Waits on this (2)

Schedule activity

No activities yet. Import a schedule to put this on the owner's critical path.