Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-LOAD
Large-load study request (interconnection request)
Not startedlibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia large-load interconnection process and terms and conditions of serviceClause
not statedTrigger
Applies at 25 MW peak load or more (GS-5 large-load threshold)Description
Formal request for Dominion to study serving the campus load: site, phasing, peak and connected MW, in-service dates. Utilities generally require site control before studying; some require zoning. Duration is for the study itself; queue position can add years and is tracked on the capacity letter class.Evidence required
Submitted load study request with Dominion acknowledgement and queue/reference number; study fee receipt.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.