Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-EQUIP
Long-lead utility equipment release (power transformers ~128 weeks, GSUs 160+ weeks)
Not startedlibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia large-load interconnection process and terms and conditions of serviceClause
not statedTrigger
Applies at 25 MW peak load or more (dedicated substation equipment)Description
Procurement gate: release of power transformers and HV breakers is tied to approval confidence because lead times (power transformers about 128 weeks, generator step-up units over 160 weeks, HV breakers 125 weeks per Q1 2026 data) exceed the entitlement cycle. Owner-furnished or utility-furnished depends on the construction agreement. Duration shown is the lead time itself.Evidence required
Purchase order release with factory slot confirmation; approval-confidence memo justifying release.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (1)
- Construction / line extension and substation agreement Not started FS
Waits on this (1)
- Energization prerequisites Not started