Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / LC-SPEX
Special exception / rezoning approval (data center use)
Not startedVetolibraryProvenance
Authority
Loudoun County, VirginiaSource document
Loudoun County Zoning Ordinance (2023), as amended March 2025 (data center by-right elimination) · 2023 ZO, 2025 data center amendment · effective 2025-03-12Clause
Loudoun Zoning Ordinance, special exception uses and procedures (2025 data center amendment)Trigger
Always appliesDescription
Discretionary legislative approval with Planning Commission and Board of Supervisors public hearings. Loudoun eliminated by-right data centers in March 2025, so every new campus is a hearing item with conditions (proffers, noise, screening, phasing). Duration estimate covers staff review cycles and two hearing bodies; actual time depends on the hearing calendar and opposition.Evidence required
Board of Supervisors approval resolution with adopted conditions/proffers; signed condition sheet; hearing minutes.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (5)
- Pre-application meeting with Planning & Zoning Not started FS
- Notice and hearing compliance plan Not started FS
- Traffic impact study Not started FS
- Noise study (generator and mechanical plant) Not started FS
- Capacity confirmation letter with energization date Not started FS
Waits on this (5)
- Appeal period expiry on entitlement approval Not started
- Site plan (STPL) approval Not started
- GS-5 large-load contract execution (14-year term, minimum demand charges) Not started
- FAA Form 7460-1 determination (airport proximity) Not started
- Condition precedent: entitlements final and appeal period expired Not started