Northern Virginia Campus — Demo
Data center · Loudoun County, VA · target energization 2029-06-30Register / DOM-COLLATERAL
Collateral posting (reported ~$1.5M per MW)
Not startedlibraryProvenance
Authority
Dominion Energy VirginiaSource document
Dominion Energy Virginia Schedule GS-5 (large general service, 25 MW+) — SCC final order in the 2025 biennial review · SCC order Nov 25, 2025 · effective 2027-01-01Clause
Schedule GS-5, security/collateral provisionsTrigger
Applies at 25 MW peak load or moreDescription
Credit support required under GS-5 before Dominion commits capital. The $1.5M/MW figure is as reported in trade press; the actual amount is set by the tariff and the customer's credit. For 150 MW that is on the order of $225M of letters of credit or cash, a lender and equity item as much as a utility one.Evidence required
Letter of credit or cash deposit receipt accepted by Dominion credit.Edit
Evidence (0)
Nothing attached. A requirement is only satisfied with evidence.
Dependencies
Must finish first (2)
- GS-5 large-load contract execution (14-year term, minimum demand charges) Not started FS
- Loan closing Not started FS
Waits on this (1)
- Energization prerequisites Not started