PowerPMIS

Northern Virginia Campus — Demo

Data center · Loudoun County, VA · target energization 2029-06-30
57 open between data date 2026-11-02 and energization · projected 2031-11-19 (623 working days late) · 10 critical · 3 veto points
#RequirementAuthorityOwnerStatusEarly startEarly finishDurFloatBlocked byNext action
1
Entitlement · LC-PREAPP
Loudoun County, VirginiaLand-use counselNot started2026-11-022026-11-30200——
2
Entitlement · DOM-LOAD
Dominion Energy VirginiaOwner's repNot started2026-11-302027-05-171200Pre-application meeting with Planning & Zoning—
3
Entitlement · DOM-CAPACITY
Dominion Energy VirginiaOwner's repNot started2027-05-172027-08-09600Large-load study request (interconnection request)—
4
Entitlement · LC-SPEX
Loudoun County, VirginiaLand-use counselNot started2027-08-092028-05-152000Pre-application meeting with Planning & Zoning; Notice and hearing compliance plan; Traffic impact study; Noise study (generator and mechanical plant); Capacity confirmation letter with energization date—
5
Permit · LC-APPEAL
Loudoun County, VirginiaLand-use counselNot started2028-05-152028-06-14220Special exception / rezoning approval (data center use)—
6
Permit · LC-SITEPLAN
Loudoun County, VirginiaLand-use counselNot started2028-06-142028-11-291200Special exception / rezoning approval (data center use); Appeal period expiry on entitlement approval; Section 404 nationwide permit verification (impacts up to 0.5 acre)—
7
Construction · DOM-CONSTRUCT
Dominion Energy VirginiaOwner's repNot started2028-11-292029-04-04900GS-5 large-load contract execution (14-year term, minimum demand charges); Site plan (STPL) approval—
8
Construction · DOM-EQUIP
Dominion Energy VirginiaProcurement leadNot started2029-04-042031-09-176400Construction / line extension and substation agreement—
9
Energization / occupancy · DOM-ENERGIZE
Dominion Energy VirginiaOwner's repNot started2031-09-172031-10-29300Collateral posting (reported ~$1.5M per MW); Construction / line extension and substation agreement; Long-lead utility equipment release (power transformers ~128 weeks, GSUs 160+ weeks); Electrical final inspection and utility release—
10
Energization / occupancy · LC-CO
Loudoun County, VirginiaPermit expediterNot started2031-10-292031-11-19150Electrical final inspection and utility release; Energization prerequisites—